Construction Updates - Active Projects

More Information
 

Construction Updates

Projects Under Construction
 

Virginia Pkwy. Lanes 5 & 6

 
 Virginia Lanes 5 and 6

 Details
  • Widen Virginia Pkwy. between U.S. 75 and Ridge Rd. from four lanes to six lanes
  • From U.S. 75 to Bellegrove Dr. the roadway will be widened to the outside of the existing pavement
  • From Bellegrove Dr. to Ridge Rd. the roadway will be widened within the existing median
  • Construction began in March 2017 with completion scheduled for February 2019
  • View FAQs
  • Project Contact  - Blake Sills, PE, 972-547-3489
    
Street Rehabilitation Projects  
 Street Rehabilitation  Details
  • On-going Street Pavement Rehabilitation and Repair along:
    • Virginia St. (Graves to Waddill)
    • Waddill St. (Virginia to Hill)
    • Valley Creek Trail (Country Club to U.S. 75)
    • Roberts Ave. (Graves to Morris)
    • White Ave. (U.S. 75 to Graves)
  • Construction schedule:
    • Virginia St. - Complete
    • Waddill St. - Complete
    • Roberts Ave. - End of March to beginning of April
    • Valley Creek Trail (Country Club to U.S. 75) - Beginning of April to end of June
    • White Ave, - Beginning of July to end of September
  • Project Contact - Nick Ataie, PE, 972-547-7637
FM 546 Replacement Project  
 FM546 Replacement  Details
  • New alignment roadway from S.H. 5 to east of Airport Dr.
  • The design for the project has been completed
  • Construction began in January 2017 and will be completed by the Summer of 2018
  • This is a TxDOT lead project. If you have any questions, please contact the TxDOT Collin County Area office at 972-542-2345
 
 
 
 
 

 

Hardin Blvd. Lanes 5 & 6

 
 Hardin Lanes 5 and 6
    
 Details
  • Widen Hardin Blvd. from S.H. 121 to McKinney Ranch Pkwy. from four lanes to six lanes
  • Widen McKinney Ranch Parkway from Hardin Blvd to U.S. 75 from two lanes to four lanes divided
  • Construction began in April 2017 and is scheduled to be complete in December 2017
  • Project Contact - Jason Horn, PE, 972-547-7435

Lake Forest Dr. Extension North

 
 Lake Forest Dr North Extension
     
Details
  • Widen Lake Forest Dr. from Wilmeth Rd. to Bloomdale Rd. from two lanes to four lanes by constructing the east half of Lake Forest Dr.
  • Construct a portion of Bloomdale Rd. east of the intersection.
  • Improvements to storm, water and illumination are also planned.
  • Construction began in August 2016 and is scheduled for completion in June 2017.
  • Project Contact - Joshua Cotton, PE, 972-547-7423
Cole Street Reconstruction  
   Cole Street Reconstruction  Details
  • Reconstruction of roadway, water and sanitary sewer along Cole St. from Bass St. to College St.
  • Construct additional storm sewer and sidewalks
  • The project is currently under construction and is scheduled for completion in August 2017
  • Project Contact - Nick Ataie, PE, 972-547-7637